The Time Has Come

Sugar Springs Property Owners Association Newsletter
The Time has Come January 2012
In This Issue
The Time Has Come
Pool Operation Schedule
Activity Center
The Pool
Heating & Air Conditioning
Locker Rooms
Activity Room & New Fitness Area
What will it cost me to use ?

The Time Has Come 

Public Meeting
It started as an idea that was approved by the membership

 

Building Footings
The idea became a project

 

New Pool from Equipment Room
The project has become a reality

 

The pool area is now ready to  open.  After three months without a pool we know that our membership cannot wait to use the new facility.

 

The new pool will officially open for use at:

 8:00 a.m.  Monday, February 6, 2012

for lap swimmers, followed by our exercise classes and open swim hours.

 

Because of the pool closure,  anyone who   purchased a 2011 Annual Swim Membership will have the expiration date extended until May 31, 2012 from the normal expiration date of February 29th. 

 

 When those individuals purchase their new 2012 membership,  you will pay 9/12 ‘s of a normal annual fee, which will then expire Feb. 28, 2013.

 

Any new memberships purchased by those not currently holding a 2011 card will pay the normal 12 month rate which also expires February 28, 2013

 

All 6 month passes and punch cards that normally expire on February 29, 2012 will also be extended until May 31, 2012.

 

 

A schedule of activity times is listed in a schedule below.

 

Pool Schedule 

 
Lap Swim:
 
Monday-Friday                   8:00 a.m. – 9:00 a.m.
 
Watercize:
Mon – Wed – Fri

9:15 a.m. – 10:15 a.m. 
10:15 a.m. – 11:15 a.m.
 
Water Aerobics:
 
Tuesday-Thursday               9:15 a.m. – 10:15 a.m.
10:15 a.m. – 11:15 a.m.
4:00 p.m. – 5:00 p.m.
 
Water Volleyball:
Men: 
Mon – Wed – Fri
11:30 a.m. – 12:30 p.m.
 
Women:
Tuesday & Thursday           11:30 a.m. – 12:30 p.m.
 
Co-ed:
Wednesday 
7:00 p.m. – 8:00 p.m.
 
Open Swim:
 
Mon-Tues-Thurs-Fri
5:00 p.m. – 8:00 p.m.
 
Wednesday                          4:00 p.m. – 7:00 p.m.
 
Saturday &  Sunday            1:00 p.m. – 8:00 p.m.
 
 
This will be the opening schedule for pool use.  This schedule will change in the future when we have a better feel of how long it takes on a daily basis to clean all of the additional space as well as when the new fitness room is completed.  The idea is to have the entire facility available for use; be it the activity rooms, fitness room or pool for everyone whenever the building is open so the operational hours will lengthen and be adjusted when that time comes.
Dear Robert,

January 25, 2012, Sugar Springs received its building occupancy permit from Gladwin County for our new pool area.  We still have a few items that need to be completed but the new pool and locker rooms are almost finished.
We have also begun work on the old pool area and this past Monday the new floor for that area was poured and we hope to have the fitness room and activity rooms completed and ready for use in April of 2012.
Please read the following articles to bring yourself up-to-date on Phase I of “the Plan for the Future.”  We will be having a “Grand Opening” sometime in May or early June to introduce the new facility to everyone.  But for now we will be opening the pool with a “soft opening” for use.
Robert Neeb CMCA, AMS
General Manager
Sugar Springs Property Owners Association 
 

Activity Center

Front Entrance
Front Entrance of New Activity Center
 
As mentioned, we have received our new building occupancy permit from Gladwin County.  Now all we have left to do is complete the few remaining items on our punch list and get our final Gladwin County Health Department approval for the pool area.  We will then be opening the doors of your new facility.
 
It has been a long process, backorders and other things beyond our control have delayed the completion but all of us involved wanted to make sure that we got the best building we could, and not sacrifice quality or budget for a faster opening.  We wanted it done right.  We know all of you will be proud of the facility when you see it and use it in the future.
 

New Pool

New Pool from Equipment Room
New pool as seen from 2nd floor equipment room

 

The new pool area as seen from the equipment room over the men’s locker room.  Note the blue ceramic tile swim lane markers for lap swimmers, the stainless steel poles that hold the volleyball net.  The area surrounding the pool has ceramic tile with in floor radiant heat.   The state of Michigan has set the occupancy of the pool at 150 people.

 The pool is the same width as the old pool but is fifteen feet shorter.  Water depth is 3′ 6″ at the shallow end and 5′ 6″ at the deep end.  The horizontal blue tile line seen in the photo marks the beginning of the decline to the deep end.  The appearance of the pool water has a darker tint to it because of the pool bottom color, the tinted pool windows and because of the high iron content in our well water.  We believe over time this condition will clear.  The water is completely safe for use. 
 The salt generator is operational as is the UV generator, which together gives us the most state of the art pool system available.  How do you make a salt water pool?  At startup you pour 2,800 lbs of food grade salt into the water.  After that the system regulates it.  This water is not salty like when you swim in the ocean.  It does not feel or taste salty.  The role of the salt is to work injunction with the UV to create very low levels of chlorine for sanitary purposes. The net result is a pool environment that is much less irritating than traditional chlorine pools.
The pool area itself is unattended but will be monitored by cameras.  Cameras will also be placed in the entrance area, fitness room as well as the two activity rooms.  You must be 18 years of age to enter the pool without an adult
Anyone wishing to enter the pool or the fitness room when completed, will be required to check in at the front desk, present their Sugar Springs Membership Card with their Annual Membership, Six Month Pass or a Punch Card.  To pay as you go, you must have your Sugar Springs Membership Card for member rates or a valid Guest Pass for guest rates.  Daily use by the public will require a drivers license or state ID card.  You will leave this card with the attendant and then be issued a locker key so that you may lock your valuables while you are using the facility.  When leaving the building you will turn your locker key back in to the attendant and he/she will return your pool membership card or in the event of a single day use, your id card or driver’s license.  We will not be renting lockers, you will need to remove all your belongings each time you visit the facility.
Pool Handicap Lift
Pool Steps and new battery powered lift
Access to the pool is gained by using the steps or in the case of someone who needs a little help, the battery powered lift on the right side of this photo, that lowers the swimmer into the water as well as lift them out when they are finished swimming.
Pool Pump Room
View of the Pool Pump Room

Have you ever wondered what makes the pool run?  The large plastic cylinder on the bottom left of the photo is one of two sand filters for the new pool.  The water from the pool is flushed through these to remove contaminates, it then passes through the silver tube in the center of the photo, which is the UV generator, which kills any remaining contaminates.  In the back left of the photo are the four salt generators which control the salt in the pool. 

Heating & Air Conditioning

Heating & Air Conditioning
Heating & Air Conditioning
The heating and air conditioning systems are housed above the men’s locker room.  This photo shows one half of that space.  There is a boiler for the pool and floor heat as well a boiler for the radiant heat that was installed in the area around the outside main entrance and another that heats the new activity rooms.  There are individual air exchangers which control the environment of the pool, the fitness center and the activity rooms.  Each is controlled individually and there are carbon dioxide sensors in each area which turn on the system by room if it senses someone breathing, all very state-of-the-art.
Any of you who saw our old pool pump room noticed how cramped and dark a workspace it was.  We made sure in this design that was changed.  You can see how open and well lit the work area is for our Building & Grounds staff to do their maintenance.

Locker Rooms

Women's Locker Room 1
A View of the Women’s Locker Room
 
The  women’s locker room view shows some of the lockers, there are 54 lockers in this room.   All rooms in the new facility, with the exception of the pool, have a lighting system that is controlled by sensors, which turn the lights on and off depending on use.  If you are the first one in a room it may be dark for a moment until the sensor picks you up and turns on the lights.  Radiant heat in the floor heats the men’s and women’s locker rooms.
 
Women's Showers
Women’s Shower Area
 
In the women’s shower area there are individual shower stalls and if you look closely you will see that there is a shower area and small dressing area in each unit.  There are two bathrooms in this area, as well as a handicap shower.  There are additional showers on the left of this photo that are out of the frame of the picture.  There is also a handicap bathroom in the shower area
Men's Locker Room 1
View of a portion of the Men’s Locker Room
The men’s locker room is set up very similar to the women’s but with a different color scheme.  There are 46 lockers in the men’s locker room.
There is also a Family/Unisex Bathroom in the main entrance area of the building.  Parents with small children or member’s needing assistance from a family member can use this bathroom.  It is handicap accessible, has a baby changing station, handicap bench and a handicap shower.
The men’s and women’s locker rooms all have handicap bathrooms, showers, handicap bench’s  and baby changing stations as well

Activity Rooms & Fitness Room

Old Pool Floor 1
A view of the newly poured old pool area

 

This a photo of the new activity area in the old pool space.  The contractor has just completed saw cutting the floor.  It is quite a change from the old pool space.  Now the walls need to be studded, insulated, drywall and the new ceiling needs to be installed.  In this westward facing photo if you look at the diamond cut in the floor you see where the sliding room divider will be installed.
 
Old Pool Floor 2
Another view of the new space (east facing view)

 

The new activity space will be comprised of 2 roughly 2,400 sq ft rooms separated by a movable room divider which will allow the entire space to become one large room.  It will also have a permanent fitness room of approximately 1,200 sq ft.  If you look on the east wall (painted circles) you can see the cutouts for the two windows in the fitness room.
Fitness Room Layout
A view of what the new fitness room will look like when completed.

 

The room will have all new commercial grade equipment, the breakdown of that equipment is:

 

                                      2 – Lower Body Arc Trainers

                                      4 – Treadmills

                                      2 – Recumbent Bikes

                                      1 – Upright Bike

                                      1 – Ab / Back Extension

                                      1 – Biceps / Triceps

                                      1 – Torso Rotation

                                      1 – Lat Pull

                                      1 – Leg Extension / Leg Curl

                                      1 – Hip Ab/Ad

                                      1 – Leg Press

                                      1 – Multi Press

                                      1 – Smith Press

 

Assorted dumbbells, Medicine balls, and a seating area when not using a machine.

 

 

What will it all cost me to use?
 
The Board of Directors previously voted to freeze all fees for the 2011, 2012, and 2013 calendar years.  With that in mind the former Pool Memberships, Passes and Punch Cards will now to be called Fitness Center Memberships, Passes and Punch Cards.  This allows the holder of any of these  memberships, passes, or punch cards to use the pool and the fitness room for one fee, which is the same as our previously published pool fees for the 2012 year.  There will be no additional charges.  Each entrant will be able to use one or both, each time they come to the facility.  We will not offer individual memberships for just the pool or the fitness room.
 
To enter the pool you must be 18 years of age or accompanied by an adult.  You must be 18 years of age or older to use the fitness room.
 
This is a great deal for individuals, families, both member and public.  We hope many of you take advantage of the facility.
 
Another change for 2012 is that anyone who purchased a tennis membership for the 2012 year will be issued a refund and once the necessary maintenance is completed, the tennis courts will be available to all members, Free of Charge.  Access to the courts will be gained by using your gate card.  Information about gate cards can be obtained from the POA office, when the necessary hardware is installed on the gate. 
 
It is hoped more members will use the fine courts and this goes along with the desire to make Sugar Springs recreational activities as inexpensive as we possibly can for the membership as a whole.
 
Should you have any questions about this or anything else in Sugar Springs call the POA office at (989) 426-4111, Monday – Friday 10:00 a.m.- 4:00p.m. 
 
 
Fitness Center Fees
Posted in Uncategorized | Tagged , , , , | Comments Off on The Time Has Come

Building Progress – August 2011

 

New Building

Building News – August 2011 
 

Our summer is beginning to wind down but the work on the new building addition is still in full swing.  The stone mason has applied the new stone facade to the existing building and the new cement siding has been added as well.  It has brought a new updated look to the restaurant.  The stone was also added to the carport area and it looks great.  There is still painting to do but it is starting to take shape nicely.
The pool company has the pool poured, the plumbing and floor heating in that area is complete.  Now that the floor around the pool has been poured, our sub-contractors can finish the steel work, and begin working on the roofing.  

The mezzanine area above the men’s locker room has also been poured; it will serve as the area where most of the plumbing and heating equipment will be housed;  those contractors will also begin to install that equipment as well.

The waterproofing, insulation, siding and stone work, and painters should also be getting started as the exterior of the building moves toward completion.

The timeline for completion of the new pool addition is still looking at an October 1st date.  When completed the work will shift to the existing pool area; its deconstruction, and re-building into the new activity area and exercise center.
Enjoy the update on the work currently going on.
Robert Neeb, CMCA, AMS
General Manager
Sugar Springs Property Owners Association
 

 

Constructing the Pool

B&B Pool Company employees applying the side walls of the new pool.  The floor of the pool is already done in this photo. 

Pool Shotcrete
Completing Pool Walls
Completing the Pool Walls

Pool wall construction almost completed by work crew.  The final finish will be one of the last items done on the project.  The day this work was done was the hottest and highest humidity day of the summer.  The crew stayed hard at work despite the sweltering temperatures.

Pool Deck Being Poured
The pool deck being poured.  While difficult to see in this photo because of its size; the floor drain that runs around the outside of the pool, radiant heat lines for the floor, stainless pool supports on the steps, ceramic tile lane lines, blue ceramic tile that is on the top edge of the pool, the anchors for the battery-operated handicap pool lift, and the bull-nose tile that caps the pool are all in place.  A ceramic tile floor will be installed on top of the concrete pool deck.
Pool Deck Poured
Lane Lines from Above
Floor Around Pool Poured

The floor around the pool has been poured. In this view if you look closely on the bottom of the pool you can see 4 of the 5 swimming lane lines that have been installed.  Holes are also in place for the aluminum volleyball posts. 

Pool Deck
The pool deck is now completed.  If you look closely the item that looks like a long piece of wood, running from bottom left to top right in the photo, is actually the new floor drain that runs completely around the pool.  The dust in the photo is a workman saw-cutting the new concrete to help convince any cracks to follow those cuts.
The concrete is now ready when it comes time to install the ceramic tile floor.
Pool Floor Poured
Drop off area stone work
New Brick and Cap Give New Look to Restaurant Drop – Off

Our stone mason sub contractor has completed most of the wall.  It is a much fresher look.  There is still painting to do on the supports and a light attached but it is looking good. 

Locker Rooms

In this view from the roof of the existing pool you can see all the concrete block work being done in the locker rooms.

The mason is working in the new women’s locker room.  The room in the background is the men’s locker room, which since this photo was taken has had a steel beamed, concrete mezzanine added, which will be the ceiling of that locker room.

 
Locker Room Block Work
Locker Room Block Work 2
Another View of the Locker Room Area
In this view of the locker rooms you can see the noches in the block for the steel beams that were later installed to support the weight of the concrete mezzaninie.
Completing Work on Concrete Mezzanine Area
This area, above the men’s locker room will house most of the mechanical equipment for the pool and heating and air conditioning for the new building.  It is spacious enough to allow maintenance plenty of room to work when needed. 

 

Mezzanine Area
No. 10 from Roof
Just Because
While they are not part of the building project, while I was on the roof I took a couple of photos that show two more beautiful recreational areas we have in Sugar Springs.
Another
Tennis and Bocci Ball courts.  From above you get a complete perspective of how wonderful our facilities really are. 

 

View of Bocci and Tennis Courts
Posted in Uncategorized | Comments Off on Building Progress – August 2011

Building Progress – July 2011

Sugar Springs Property Owners Association 
July, 2011
Construction Sign
SS Logo - Debbie 
The work on the the new building project has been progressing well and is on budget.  The mason’s have erected most of the exterior block of the new structure; the radiant heat and in-floor plumbing for the locker room is in place; the in-ground electrical in that area is done as well.
  
The building steel has been erected; the old roof cut away to allow a firewall to be constructed; the cultured stone is now being applied.  The new concrete siding has been attached to the existing restaurant, new eye brows also have been added to break up the siding.  The old wooden windows on the south side of the restaurant are not going to be replaced.  The decision was made to just repaint them.  In Phase II all the windows will be removed because the wall they are on will be restrooms, and no windows will be needed.
  
The new pool itself was dug, prepared for shotcrete to be applied.  This part of the project has not gone according to our timetable but by working on other parts of the plan we are still on schedule.  The fault has not been with our project manager or the pool sub-contractor but rather with the permit process in Lansing.  We were told that it should take between 6-8 weeks for approval and we are now over 12 weeks and no permit has yet been issued.  We know that they have looked at the design drawings and made no requests for any substantial corrections.  While we still expect the permit, “any day”, the process has been frustrating.
  
It is fun to now walk in the building through the new entrance, walk into the locker rooms, showers, pool area and pass down the hallway to the door to the new workout area.  While everthing is not complete, it is easy to visualize all those when you are in the construction area.
  
I want to thank the members of the project workgroup for volunteering their time to help ensure that Sugar Springs gets exactly what it expects during all phases of the project.  Steve Lucas, Larry Fees, Vern Purdy, Sandy Berger, Sandy Stegeman, Jim Jones, and Paul Daugherty have given their time to date, and others will come on board as other parts of the project move forward.  “Thank you”, to all of you for your help.  Not one of these individuals had any hestitation when asked to help, despite the knowledge that it would involve a considerable amount of their time.  This is just another wonderful example of the volunteer spirit that is alive and well in Sugar Springs, whether it is through one of our many committees or done on an individual basis.
  
  
Sincerely

 Robert Neeb, CMCA, AMS

General Manager

Sugar Springs Property Owners Association
(989) 426-4111

 

 
We have progressed from this
Building Footings
  
  
  
  
  
  
  
  
  
  
  
  
A view of the building site from the roof of the existing pool showing footings preparation. 
To This !
Early July Building
  
  
  
  
  
  
  
  
  
  
  
  
 
Exterior block walls being laid, new pool being dug, floor of new entry, and locker rooms.  On this day there were 16 worker’s in this small area.
And now this
Steel Structure
  
  
  
  
  
  
  
  
  
  
  
  
 
The steel is erected, ready for roofing 
 
The Floor is preparedRadiant Heat in Locker Room
  
  
  
  
  
  
  
  
  
  
  
  
Before the locker room and entry way floor was poured, insulation, plumbing and radiant heat lines needed to be installed.  

 

New Pool Ready for ShotcretePool Ready for Shotcrete
  
  
  
  
  
  
  
  
  
  
  
  
  
Eyebrows installed on existing buildingExisting Building Eyebrows
  
  
  
  
  
  
  
  
  
  
  
  
A view of the new eyebrows on the existing building which are intended to break up the long runs of our new concrete siding, and the new siding
New Cultured StoneNew Cultured Stone
  
  
  
  
  
  
  
  
  
  
  
  
 
The beginning of installation of the cultured stone that will be installed on the existing and new building
New Siding and Trim at Restaurant Main EntranceNew Siding at Main Entrance
  
  
  
  
  
  
  
  
  
  
  
  
 
 

Join Our Mailing List

Please Use Caution
With the construction now started please use extreme caution around the construction site; whether you are golfing, walking, or even driving by.
  
I’m sure that there will be a great deal of curiosity during construction but no one not directly involved in the construction project is permitted on the construction site.  Please look from beyond the fencing surrounding the site.
  
Because this is a construction site, hardhats must be worn
  
  SLOW DOWN on the highway when going past the restaurant.
  
The old entrance to the Hearth, Golf Course, and Pool has been closed for the entire time of construction.  All patrons for will now enter and exit from the west – the old EXIT.  Be sure when exiting that you stay over on the right side and don’t block others from entering. 
 
 
 
 Because of the loss of the old pool parking lot, the main lot will be more heavily used, particularly during the weekday mornings.  Morning golfers please start in the morning by filling the parking spaces on the west side of the parking lot to allow the morning swimmers to park closer to the pool area.  Golfers, also do not park in the area designated for the restaurant.  If additional parking is needed in the mornings drop off your clubs and park in the lower parking lot.  Self-police yourself and your other fellow members to follow the listed parking rules.  We will be relining the parking lines next week to assist everyone to also park between the lines and which angle to park. 
  
This entrance change is sure to confuse some, so PLEASE slow down, when passing in front of the golf course and restaurant because someone may pull the unexpected in front of you.
  
  
Posted in Uncategorized | Comments Off on Building Progress – July 2011

Construction Progress – May 20, 2011

Sugar Springs Property Owners Association 
May 20, 2011
Construction Sign
SS Logo - Debbie
This past week there has been a flurry of activity at the construction site.  The footings and piers were formed, and then poured.  The masons came in and put it the block wall up to grade.  The walls were then waterproofed and insulated. 
  
The original stone was removed from the existing building and the carport area, the exterior plywood was exposed for inspection.  A few small areas were found to have deterioration because of water damage, that will need to be repaired.  The amount of repair work was smaller than I anticipated considering the age of the building.
  
The footings and block were backfilled with sand and by week’s end will be ready for the plumbing and electrical sub-contractors to come in and do their work that must be completed before the floor of the entry and locker room areas is poured to final grade.  All this work is being done under the watchful eye of our testing company to make sure that everything is done to architectural specifications.
  
The stone sub will be coming in to prep the area for the cultured stone; another will repair the damaged plywood and do other prep work preparing to apply to apply the concrete siding to the existing building. 
  
In short, we are really gearing up and work is progressing very well.  We have been fortunate that the weather has been in our corner; it may have been chilly but we have lost no work time because of rain.
  
Sincerely

Robert Neeb, CMCA, AMS

General Manager

Sugar Springs Property Owners Association
(989) 426-4111

 
Beginning Work On Building Footings
Building Footings
  
  
  
  
  
  
  
  
  
  
  
 
A view of the building site from the roof of the existing pool showing footings preparation. 
Footings Preparation Up Close
Footing & Re-Rod Preparation
  
  
  
  
  
  
  
  
  
  
  
  
This photo shows the wooden framing that along with the steel rod forms the footings.
Poured Footings
Poured Footings
  
  
  
  
  
  
  
  
  
  
  
After the footings were poured the forms were removed and this is the result.  The new structure will rest on these footings   
A View Of The Block Work From AboveTop View of Block Work
  
  
  
  
  
  
  
  
  
  
  
  
A view from above of the block work being done   
Another View Of The Block Work From AboveAnother View of Block work
  
  
  
  
  
  
  
  
  
  
     
Building Siding and Stone RemovalBuilding Stone Removal
  
  
  
  
  
  
  
  
  
  
  
  
 
A view of the stone and old building siding removed (Note the small area of wood rot in the lower right hand corner of the picture)
Building Siding and Stone RemovalStone and Siding Removal from the Car Port Area
  
  
  
  
  
  
  
  
  
  
  
  
A wider angle view of the stone and siding removal
Stone Being Removed From Car PortCarport Area
  
  
  
  
  
  
  
  
  
  
  
   
Stone Removed From Front Entrance AreaStone Removed From Front Entrance
  
  
  
  
  
  
  
  
  
  
  
  
Stone Removed From CarportStone Removed From Carport
  
  
  
  
  
  
  
  
  
  
  
  
Work Crew Bringing Sand Up To GradeWork Crew Working Sand
  
  
  
  
  
  
  
  
  
  
  
     
Ready for Plumbers and Electricians to begin their work.Ready for Plumbing and Electrical
  
  
  
  
  
  
  
  
  
  
  
    
 

Join Our Mailing List

Please Use Caution
With the construction now started please use extreme caution around the construction site; whether you are golfing, walking, or even driving by.
  
I’m sure that there will be a great deal of curiosity during construction but no one not directly involved in the construction project is permitted on the construction site.  Please look from beyond the fencing surrounding the site.
  
Because this is a construction site, hardhats must be worn
  
  SLOW DOWN on the highway when going past the restaurant.
  
The old entrance to the Hearth, Golf Course, and Pool has been closed for the entire time of construction.  All patrons for will now enter and exit from the west – the old EXIT.  Be sure when exiting that you stay over on the right side and don’t block others from entering. 
 
 Because of the loss of the old pool parking lot, the main lot will be more heavily used, particularly during the weekday mornings.  Morning golfers please start in the morning by filling the parking spaces on the west side of the parking lot to allow the morning swimmers to park closer to the pool area.  Golfers, also do not park in the area designated for the restaurant.  If additional parking is needed in the mornings drop off your clubs and park in the lower parking lot.  Self-police yourself and your other fellow members to follow the listed parking rules.  We will be relining the parking lines next week to assist everyone to also park between the lines and which angle to park. 
  
This entrance change is sure to confuse some, so PLEASE slow down, when passing in front of the golf course and restaurant because someone may pull the unexpected in front of you.  
Posted in Uncategorized | Comments Off on Construction Progress – May 20, 2011

The Start of Construction

Sugar Springs Property Owners Association 
May 3, 2011
Construction Sign
SS Logo - DebbieConstruction has begun on Sugar Spring’s new pool, activity/exercise area.  The construction team will be putting their early focus on site preparation, digging and pouring footing, removing existing brick and stone from the building. Attached are a few early photos.
  
FED, our Construction Manager, their assigned project manager, and their on-site manager will be monitoring the work and progress of our sub-contractors making sure that not only do things get done in accordance with our design, but also that the project stays within our timeline for completion, and is completed within the budget that was established for this phase of the project.  The original timeline puts completion sometime in October, however the new pool and locker rooms will be completed prior to that.  We won’t start in the new Activity/Exercise area until the new building portion of the project is occupied.
  
Our own Sugar Springs construction team, made up of members, who have previous project management experience, in these types of projects, along with the General Manager, B&G Supervisor, and Treasurer, will also be monitoring the project on a daily and weekly basis to make sure that Sugar Springs has the best possible addition to our facilities. Your Board of Directors, and you the membership, will also be updated regularly, on the progress, as our project moves forward.
  
We have an excellent team put together to make a great “project” into the finished product.  A great number of members have stepped forward and expressed interest in serving on this team, and while that interest is appreciated, it is difficult to accept all your help because the team would be too large to be effective.  But again, thank you for volunteering, and if the need arises that additional expertise is needed, we certainly know where to go to get it.
It will be an exciting summer as the project hits full swing.
  
Sincerely,

 

Robert Neeb, CMCA, AMS
General Manager
Sugar Springs Property Owners Association
(989) 426-4111

 

 
Interior Color Palette
New Building Color Palette
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
 
  
  
  
  

The Color Palette does not reproduce well but it does show the earth tone theme that will be carried thoughout the new building and activity areas.

Goodbye Old Brick
Brick Removal
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
In preparation for the installation of the new concrete siding the existing brick on the south, east and west walls of the building must be removed.  In the area pictured a new concrete fire wall will be constructed.

 

Plants, Shrubs, and Stone Must Go Too
Stone
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
Because the original stone could not be matched, the existing stonework on the south and west side of the building will also be replaced. New cultured stone will be put up in its place.  Because of this and the siding work that will also be occurring all our plants and shrubs had to be removed.  Building & Grounds has placed them in mulch to attempt to keep them alive for replanting when the time is right.  Pictured above is the lone survivor.
  

 

Digging the new building footingsDigging Footings
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
 
  
  
  
Workmen digging some of the areas where new footings are going to be poured to support the steel structure of the new building.  

 

 

Join Our Mailing List

Please Use Caution
With the construction now started please use extreme caution around the construction site; whether you are golfing, walking, or even driving by.
  
I’m sure that there will be a great deal of curiosity during construction but no one not directly involved in the construction project is permitted on the construction site.  Please look from beyond the fencing surrounding the site.
  
Because this is a construction site, hardhats must be worn
  
  SLOW DOWN on the highway.
  
The old entrance to the Hearth, Golf Course, and Pool has been closed for the entire time of construction.  All patrons for will now enter and exit from the west – the old EXIT.  Be sure when exiting that you stay over on the right side and don’t block others from entering.
  
This entrance change is sure to confuse some, so PLEASE slow down, when passing infront of the golf course and restaurant because someone may pull the unexpected in front of you.
  
  
Posted in Uncategorized | Comments Off on The Start of Construction

Groundbreaking Photo

Posted in Uncategorized | Comments Off on Groundbreaking Photo

Groundbreaking

The ceremony marking the official groundbreaking for the Sugar Springs building project was held Thursday, April 21st.

To view the ceremony click on the link below:

http://www.youtube.com/watch?v=PbVwNqJTN7o

Posted in Uncategorized | Comments Off on Groundbreaking

We’re Getting Started

Our Building & Grounds Department is shown removing our three flag poles and sod from the area where the new pool will be constructed.  It is our understanding that frost laws will be removed sometime next week so things will really start happening.  Everyone is very excited to get going – Robert Neeb, General Manager

Posted in Uncategorized | Comments Off on We’re Getting Started

Bidding Packages Available at FED Corporation

March 23, 2011

Bid packages are now available at FED Corporation, Gladwin, MI for our project construction.  All bids are required to be turned in to FED no later than April 6th.

In other developments; the Gladwin County Zoning Department requested that the parcel that the Hearth Restaurant, new construction area, and the Pro Shop sit on, be rezoned from D-1 to B-1 prior to their approving our construction plans.  The Association has submitted all paperwork necessary and final approval is expected April 6, 2011.

We hope to begin construction shortly after that date, however local load restrictions will, to a large extent, determine our start date.

Posted in Uncategorized | Comments Off on Bidding Packages Available at FED Corporation

Pool Contractor Chosen

Subject: Sugar Springs Awards Pool Contract to B & B Pools of Livonia, MI.

Today, Sugar Springs General Manager, Robert Neeb, announced that the first major contract for their new year-round swimming pool was awarded to B & B Pools of Livonia, MI.  B & B was selected after in-depth consideration of six different pool contractors from around the state, by FED Corporation of Gladwin and the Sugar Springs team.

The new pool will use the latest technology for water purity and safety. A saltwater and UV purification system will be used to virtually eliminate the need to add chlorine or bromine to the pool, which is known to cause skin and respiratory problems. Handicap access will be provided via a chair lift at the side of the pool near the entrance steps.

More on B & B Pools

B&B Pool Co. has been in the commercial and residential construction, renovation, service and supply business. As the company matured, the focus of the business shifted to concentrate more on the commercial construction and renovation business. B&B Pool Co. has built some of Michigan’s most impressive aquatic facilities, including those for Ann Arbor’s Pioneer High School, which has one of Michigan’s top rated competitive swimming programs. Pioneer’s pool is a14-lane, state-of-the-art competitive swimming and diving facility.

Other projects for B&B Pool Co. include Delta College’s new indoor water park pool that combines SCS play features in a zero entry area with a White Water Industries water slide, a lazy river ride area, a whirlpool, lane swimming, one-meter diving and a movable bulkhead. B&B Pool Co. also built the entire natatorium area for the new Lake Orion High School, which included an 11-lane competitive pool with one- and three-meter diving and a separate four-lane warm-up pool with four more 75-foot long lanes and a handicap ramp.

Posted in Uncategorized | Comments Off on Pool Contractor Chosen